2021 PMP Street and Utility improvements

Subscribe for Updates

To receive emails or texts about street and utility improvements, subscribe here.

Sodding of All Phases Beginning Monday, September 20th

Phases 1A and 1B—Glenpaul 
Starting Monday of next week, crews are scheduled to begin placing sod in boulevard areas that were disturbed by construction. They are tentatively planning to finish this phase around mid-week. 

Phase 2—Jerrold
Throughout the week, crews worked on adding topsoil in the boulevards, prepping it for sod. Crews began yesterday paving the asphalt trails and driveways, and plan to be finished by the end of the day today. Towards the end of next week, sodding crews will begin restoration work in boulevard areas that were disturbed by construction.

Phase 3—Prior
This past week, crews worked on adding topsoil in the boulevards, prepping it for sod. Crews began yesterday paving the asphalt trails and driveways, and plan to be finished by the end of the day today. Towards the end of next week, sodding crews will begin restoration work in boulevard areas that were disturbed by construction.

Phases 4A and 4B—Edgewater
Yesterday, paving crews patched asphalt trails and driveways that were disturbed by the spot curb replacement. By mid-week next week, crews are tentatively scheduled to begin placing sod in boulevard areas that were disturbed by construction.

New Sod Warranty: Once sod is placed at your property, it will be under warranty by the contractor for 30 days. Over that time, they will water the sod and make sure the sod takes. Next week when the sod is installed, be on the lookout for notices at your door, on guidance for taking care of your new sod.

Traffic Safety: Please be aware of construction crews and their equipment. If crews are blocking off certain portions of the street while they are working, give them the proper space and time to see you, so they can safely guide you through the construction areas. 

Please reach out to Brian Schmit (612-368-1228) or Nick Amatuccio (612-965-3926) with Bolton & Menk or David Swearingen (651-792-7847) with the City of Arden Hills if you have any questions about the project.

https://www.cityofardenhills.org/2021PMP

Paving of Phases 2 and 3 Saturday, September 11th; Patching of Asphalt Driveways in Phases 2 and 3 – Week of September 13th

Phases 1A and 1B—Glenpaul 
Next week, no major work is scheduled in this area. Sod is scheduled to be placed the week of September 20th.

Phase 2—Jerrold 
Throughout the week, road crews added the last portion of gravel to the street and prepped it for paving. Paving of the first lift of asphalt is scheduled for this Saturday, September 11th. 

Next week, crews will be working in the boulevards grading out topsoil, prepping the restoration areas for sod. On Wednesday, September 15th, crews are tentatively scheduled to be patching the asphalt driveways back.

Phase 3—Prior
Throughout the week, road crews added the last portion of gravel to the street and prepped it for paving. Paving of the first lift of asphalt is scheduled for this Saturday, September 11th. 

Next week, crews will be working in the boulevards grading out topsoil, prepping the restoration areas for sod. On Wednesday, September 15th, crews are tentatively scheduled to be patching the asphalt driveways back.

Phases 4A and 4B—Edgewater
Next week, no major work is scheduled in this area.

Concrete Curb and Driveway Finishing in Phases 2 and 3, Preparing for Paving in Phases 2 and 3 – Week of September 6th *No work will be occurring on Monday, September 6th due to the Labor Day Holiday**

Phases 1A and 1B—Glenpaul
Finishing irrigation repairs and landscaping next week in preparation for sod installation in September. 

Phase 2—Jerrold
Throughout the week, concrete crews worked on installing the curb and gutter, followed by the driveways today. Weather permitting, all of the concrete curb and driveways will be finished by tomorrow.

Towards the end of next week, road crews will be adding the last portion of gravel to the street, in preparation of paving the following week. Also during this time, be on the lookout for crews removing the tape from the entrance to driveways, signifying the concrete is good to drive over.

Phase 3—Prior
Throughout the week, concrete crews worked on installing the curb and gutter, and followed with the driveways, finishing them today. 

Towards the end of next week, road crews will be adding the last portion of gravel to the street, in preparation of paving the following week. Also during this time, be on the lookout for crews removing the tape from the entrance to driveways, signifying the concrete is good to drive over.

Phases 4A and 4B—Edgewater
Concrete crews finished the remaining spot curb replacement this week. Next week, no major work is scheduled in this area.

Concrete Curb and Driveway in Phases 2 and 3 – Week of August 30th

Phases 1A and 1B—Glenpaul 
Finishing irrigation repairs next week in preparation for sod installation in September.

Phase 2—Jerrold
On Monday of this week, the street crews finished adding gravel to the road, prepping it for curb. 

Concrete crews are scheduled to begin installing curb and gutter at the road edge Monday next week, weather permitting. They then would pour the concrete driveways and aprons the following days once curb is finished. Please be on the lookout for notices at your door, with more information on the concrete installation, length of time to stay off the concrete, and parking during this time. Note, the current no parking signs up on the entrances of the neighborhood are for state fair parking, and do not pertain to residents using street parking due to construction.

Phase 3—Prior
On Monday of this week, the street crews finished adding gravel to the road, prepping it for curb. Sewer crews throughout the week lined the existing sanitary pipe on Prior, and plan on finishing by tomorrow, 8/27. 

Concrete crews are scheduled to begin installing curb and gutter at the road edge Monday next week, weather permitting. They then would pour the concrete driveways and aprons the following days once curb is finished. Please be on the lookout for notices at your door, with more information on the concrete installation, length of time to stay off the concrete, and parking during this time. Note, the current no parking signs up on the entrances of the neighborhood are for state fair parking, and do not pertain to residents using street parking due to construction.

Phases 4A and 4B—Edgewater
Concrete crews are scheduled to finish the spot curb replacements next week.

Paving on Phases 4A and 4B Tomorrow, August 20, Road work on Phases 2 and 3 Finishing—Week of August 23 

Phases 1A and 1B—Glenpaul    
Throughout the week, crews intermittently worked on cleaning up the boulevards and grading out topsoil, in preparation of sod. Today, the permanent mailboxes were reinstalled and the temporary boxes taken down. By tomorrow, all mail should be back to being delivered to your normal mailbox. Next week, no major work is scheduled in this area.

Phase 2—Jerrold
Throughout the beginning of the week, road crews finished building the road and adding gravel to the street, in preparation of curb and cutter installation. Tomorrow, street crews will pave the base course on the west end of Jerrold (Phase 4B). While paving, please be prepared for short periods of time where portions of the road will be closed, to give the asphalt proper time to cool down and be compacted. Next week, no major work is scheduled in this area.

 Phase 3—Prior
This past week, road crews worked on building the road and adding gravel to the street. By the end of the week, they plan on having the entire street to a gravel surface.

On Monday, the road crews will be finishing adding gravel to the street, and fine tuning the road for curb and gutter. Starting Tuesday, and continuing throughout the week, sewer crews will be working on lining the existing sanitary pipe on Prior. The lining work is completely underground, therefore no major traffic disruptions are expected.

Phases 4A and 4B—Edgewater
Throughout the week, road crews worked on grading out the existing reclaimed surface, getting the street ready to pave. Tomorrow, street crews will pave the base course on both blocks of Edgewater. While paving, please be prepared for short periods of time where portions of the road will be closed, to give the asphalt proper time to cool down and be compacted. Next week, no major work is scheduled in this area.

Roadwork Continuing on Phases 2 and 3; Paving on Phases 4A and 4B—Week of August 16

Phases 1A and 1B—Glenpaul              
Throughout the week, crews worked on cleaning up the boulevards and grading out topsoil, in preparation of sod. Today, crews will finish paving all the asphalt driveways, and they will be opened back up by the end of the day.

Next week, crews will continue work in the boulevards, adding topsoil and prepping for sod.

Phase 2—Jerrold 
Throughout the week, road crews worked on building the road and adding gravel to the street. By the end of the week, they are planning to have both blocks to a gravel surface.

Next week, street crews will continue adding to the street, prepping it for curb and gutter. Paving crews are tentatively scheduled to pave the base course of asphalt on the west end of Jerrold (Phase 4B) by mid-week.

Phase 3—Prior
This past week, road crews worked on stripping off the reclaim material and began getting ready to build the street.

Next week, crews plan to build the street back up to a gravel surface, in preparation of curb and gutter.

Phases 4A and 4B—Edgewater
Today, a reclaimer will be onsite grinding up the existing pavement on the street into a gravel surface.

On Monday and Tuesday of next week, street crews will be fine tuning the gravel surface, prepping it for paving. By mid-week, crews are tentatively scheduled to pave the base course of asphalt on both blocks of Edgewater. 

Utility Work Finishing on Phase 2 and 3; Roadwork on Phase 2—Week of August 9

Phases 1A and 1B—Glenpaul              
Concrete crews finished pouring the curb and driveways on Monday this past week. Road crews arrived onsite soon after, grading and prepping the street for paving. On Friday, crews will pave the base course of asphalt on both blocks of Glenpaul. Residents on Glenpaul can access their driveways again after paving is complete.

Phase 2—Jerrold reconstruction area east of cul-de-sac
Storm sewer installation on the east block of Jerrold was finished on Thursday. Crews plan to have all temporary water disconnected by tomorrow on both blocks.

Starting Monday of next week, crews will begin building the road and getting the road to a gravel surface, starting at New Brighton and working their way west.

Phase 3—Prior
From the beginning to the middle of the past week, utility crews finished the storm sewer installation and watermain replacement on Prior.

Road crews are tentatively scheduled early next week, to strip off the remaining reclaim material on Prior from County Rd D to Glenpaul.

Phases 4A and 4B—Edgewater and Jerrold area west of cul-de-sac
Spot curb replacement was finished on Monday, for both blocks of Edgewater. On Tuesday this past week, the watermain was replaced in the intersection of Prior and Edgewater.

On Thursday of next week (8/12), crews are scheduled to reclaim (grind up) the remaining asphalt street pavement.

Utility Work Continuing on Phase 2 and Phase 3; Paving on Phase 1—Week of August 2

Phases 1A and 1B—Glenpaul              
Concrete crews started pouring the curb and gutter today, and will finish tomorrow and start pouring driveway aprons. Residents on Glenpaul can park in front of the new curb over the weekend.

Concrete crews will finish pouring the concrete driveways early next week if they don’t finish on Friday, and access to driveways are anticipated to be open by the end of next week. Asphalt paving is scheduled to occur on Friday, August 6. Street grading to prepare for paving will occur Wednesday and Thursday of next week.

Phase 2—Jerrold 
Watermain and water services were installed on the east block of Jerrold this week. Watermain and water services on the west block of Jerrold have started and are scheduled to be complete by the end of this week.

Next week, utility crews will begin installing storm sewer on the east block of Jerrold and at the intersection of Prior and Jerrold. Utility work is anticipated to wrap up by the end of next week or the following week. 

Phase 3—Prior
Prior Ave was reclaimed earlier this week to grind up the existing pavement into a gravel surface.

Utility work will begin next week with watermain replacement at the intersection of Edgewater and Jerrold, and storm sewer replacement north of Glenpaul. Utility work is anticipated to wrap up by the end of next week or the following week.

Phases 4A and 4B—Edgewater
Spot curb replacement will occur later this week and early next week. The watermain will be replaced in the intersection of Prior and Edgewater early next week.

Utility Work Continuing on Phase 2,
Phase 3 Starting Up —July 26

Phase 1A—East Block of Glenpaul
On Thursday and Friday of next week, concrete crews are scheduled to be onsite. They will begin with installing the curb and gutter at the road edge, and then plan on pouring the concrete driveways on Friday. Please be on the lookout for notices at your door, with more information on the concrete installation, length of time to stay off the concrete, and parking during this time. 

Phase 1B—West Block of Glenpaul
On Monday, utility crews finished the storm sewer on Glenpaul at the intersection with Prior. From Monday through Thursday, the road crew worked on building up the street to a gravel surface, starting just off Cleveland, and finishing right before Prior. The crews will continue to fine tune the road and prep driveways on Friday, in preparation of the curb and gutter.

On Thursday and Friday of next week, concrete crews are scheduled to be onsite. They will begin with installing the curb and gutter at the road edge, and then plan pouring the concrete driveways on Friday. Please be on the lookout for notices at your door, with more information on the concrete installation, length of time to stay off the concrete, and parking during this time. 

Phase 2—Jerrold 
At the beginning of this week, crews completed making the temporary water hookups to each individual home. By Tuesday and Wednesday, utility crews started working on making the watermain connections to the existing lines, just off of New Brighton and at the west block of Jerrold. They plan on continuing watermain installation on Friday, picking up where they left off and heading west towards Prior.

Next week, utility crews will continue installing watermain on the east block of Jerrold. Once that is complete, they will put in the individual water services to each house. By the middle to the end of the week, they will then move to watermain on the west block of Jerrold. 

Phase 3—Prior
On Wednesday of next week (7/28), crews are scheduled to reclaim (grind up) the existing asphalt street pavement from Jerrold to County Road D. NOTE: this reclamation work is a couple of weeks ahead of schedule, compared to what was originally planned. After the road is reclaimed, residents will be able to drive and park on the gravel surface until utility work begins.

Phase 4A—West Block of Edgewater
Throughout the beginning of the week, utility crews finished the sanitary forcemain installation and filled in the pits.

On Wednesday and Thursday of next week, crews are tentatively scheduled to remove small portions of existing curb that is marked for replacement.

Phase 4B—East Block of Edgewater 
On Wednesday and Thursday of next week, crews are tentatively scheduled to remove small portions of existing curb that is marked for replacement.

Utility Work Starting in Phase 2 —July 20

Phase 1A—East Block of Glenpaul
At the beginning of the week, crews finished getting the road to a gravel surface, stopping just before the intersection with Prior. On Wednesday, they worked on finetuning the road in preparation of curb installation and paving.

By the end of this week, following into Monday of next week, utility crews will install storm sewer improvements around the intersection of Prior and Glenpaul. Once that is done, no major construction is scheduled for the remainder of the week.

Phase 1B—West Block of Glenpaul
On Monday and Tuesday, utility crews finished installing water services on the east half of the block. Utility crews then moved to installing the storm sewer improvements, starting at Cleveland and making their way east towards Prior. By Friday, crews hope to be at the intersection of Prior with the storm sewer. Also on Friday, crews will begin on building the road and getting the road to a gravel surface, starting near Cleveland and working their way east. 

On Monday of next week utility crews will finish storm sewer installation in the intersection of Prior. Road crews will additionally continue working on building up the street, and are aiming to have the entire block to gravel by Thursday. All necessary testing on the watermain is scheduled to be completed by early next week, in which then all residents will be taken off temporary water.

Phase 2—Jerrold 
At the beginning of this week, crews finished setting up of the temporary water, and testing of the temporary lines began. On Thursday, road crews worked on stripping off the reclaim material on the street, in preparation of watermain installation. By the end of this week, into Monday of next week, crews plan on making the temporary water hookups to individual homes.

On Tuesday of next week, utility crews are scheduled to begin watermain work on the east end of the east block, off New Brighton. Please be on the lookout for notices at your door, for details regarding the water shutdown needed, for crews to start their work. Watermain installation will continue throughout the week on the east block of Jerrold, followed by water service replacement.

Phase 4A—West Block of Edgewater 
This past Monday, the bypass for the sanitary forcemain was installed, from mid-block, to the west through the cul-de-sac. Pipe Bursting crews then arrived on Tuesday, excavating the necessary pits and potholing for any small utilities that would be in conflict with their trenchless work on the forcemain.

On Monday of next week, the pipe bursting crews are scheduled to finish with the rehabilitation of the forcemain, and utility crews will follow to fill in the pits. By mid-week, all of the pits should be backfilled, and the road will be put back to a gravel surface.

Utility Work Starting in Phase 4A —July 12

Phase 1A—East Block of Glenpaul
At the beginning of the week, crews finished taking all the properties off temporary water and all normal water services where then turned back on in Phase 1A. Throughout the week, road crews worked on constructing the road and building it up to the gravel base, starting at New Brighton and finishing just short of Prior. 

Around mid-next week, just off of Prior, utility crews will install storm sewer improvements around the intersection with Glenpaul. Road crews will also be working on the block throughout the week, fine tuning the road, in preparation of curb installation and paving.

Phase 1B—West Block of Glenpaul
This week, utility crews finished installing the watermain from mid-block to Prior. They then began putting in the remaining water services on the east side of the block.

In the upcoming week, utility crews will finish water service installation. Once that is done and all necessary testing is complete, residents will be taken off temporary water. Starting mid-week, utility crews will then begin the storm sewer improvements on the west end of the block and make their way east. The crews are tentatively scheduled to finish the storm sewer at the intersection with Prior by the end of the week, which would then complete all utility work in Phase 1B.

Phase 2—Jerrold 
On Thursday and Friday of this week, crews reclaimed (grinded up) the existing asphalt street pavement from New Brighton to just short of the cul-de-sac on the west block. During this, temporary water installation also began.

Once the temporary water is setup, and testing complete, crews plan on making the hookups to individual homes late next week or possibly at the beginning of the following week. Be on the look-out for notices at your door, regarding more information on timing and details of the individual hookups to each house. Temporary mailboxes will also be set up on Prior Ave between Glenpaul Ave and County Rd D starting on Monday 7/12, and will remain in place during the construction of Phase 2.

Phase 4A – West Block of Edgewater
On Friday, crews reclaimed (grinded up) a strip of the existing asphalt on the north side of the road, in preparation of the sanitary forcemain bypass installation the following week.

Starting on Monday of next week, the bypass for the sanitary forcemain will be installed from around mid-block to the west, through the cul-de-sac. Trenchless rehabilitation work on the forcemain is tentatively scheduled to begin on Tuesday and continue throughout the remainder of the week.

Phases 2 and 4A Starting Up—July 8

Phase 1A – East Block of Glenpaul
Last week, utility crews installed new storm sewer on the east end of Glenpaul, near New Brighton. Crews worked on the remaining few service connections on the block. All the properties in Phase 1A are off temporary water, and all water services are turned back on.

Road crews are starting this week, to begin constructing the road, starting at New Brighton and then working their way west. By the end of the week or early next week, the contractor is planning to have the road completely covered with gravel, in preparation of the curb installation and paving.

Phase 1B –West Block of Glenpaul
Last week, utility crews made connections with the new water services to the existing lines at each property on the west half of the block. A portion of the storm sewer improvements was installed on the west end of Glenpaul, right off of Cleveland, to aid in drainage of the roadway.

This week, utility crews will continue with watermain installation from mid-block towards Prior. Once that is complete, they are scheduled to begin putting in the remaining water services on the east side of the block. Once all the water main and water services are installed and all necessary testing is complete, residents will be taken off temporary water.

Phase 2 - Jerrold
On Thursday (7/8), a day later than previously scheduled, crews are scheduled to reclaim (grind up) the existing asphalt street pavement from New Brighton to just short of the cul-de-sac on the west block. Temporary water setup on Jerrold will also begin that same day, with hookups to individual homes occurring on Friday or at the beginning of the following week. 

Phase 4A – West Block of Edgewater
On Thursday (7/8), a day later than previously scheduled, crews are planning to reclaim (grind up) a strip of the existing asphalt on the north side of the road, in preparation of the sanitary forcemain bypass installation the following week.

Safety First! Please be aware of construction crews and their equipment. If crews are blocking off certain portions of the street that you need to walk or bike through, please talk to one of the workers onsite to ensure all equipment is aware of you passing through.

Utility Work Continuing—June 28

Phase 1A – East Block of Glenpaul

Earlier this week, utility crews made connections with the new water services to the existing lines at each property.

Beginning next week, crews will install the storm sewer within the street and boulevard near the intersection of New Brighton and should be finished mid-week. Road crews are tentatively scheduled to arrive onsite Thursday of next week, to begin constructing the road, starting at New Brighton and then working their way west. By the end of the week, the contractor is planning to have all the properties in Phase 1A off temporary water, and all water services will be turned back on.

Phase 1B –West Block of Glenpaul
On Thursday and Friday of this week, utility crews began installing the new watermain, starting at Cleveland and working their way east toward Prior Ave.

By around mid-week next week, utility crews will pick up where they left off on Friday, and continue with watermain installation. Once that is complete, toward the end of the week, water service installation will start. Be on the lookout for notices at your door to notify you about possible water shutdowns to individual houses so crews can connect the new water services to your existing lines. Once all the water main and water services are installed and all necessary testing is complete, residents will be taken off temporary water.

Utility Work Continuing—June 21

Phase 1A – East Block of Glenpaul
On this past Monday, hookups from the temporary water to the individual houses were made, while a road crew stripped off reclaim material from the road. Throughout the remainder of the week, utility crews installed watermain, starting at the connection on New Brighton and ending at the intersection with Prior Ave.

Beginning next week, water service installation will start and is estimated to finish by mid to late week. Be on the lookout for notices at your door, to notify you about possible water shutdowns to individual houses so crews can connect the new water services to your existing lines. Once all the water main and water services are installed and all necessary testing is complete, residents will be taken off temporary water.

Phase 1B –West Block of Glenpaul
Throughout this last week, road crews stripped off reclaim material from the road. On Thursday, the temporary water setup was finished and connections to individual houses were made. On Friday, 6/18, utility crews will make the watermain connection at Cleveland Ave, and replace a sanitary manhole at the same intersection. 

Crews are estimating to begin the watermain installation on this block by late next week. They are tentatively planning to start at the Prior Ave intersection, where they left off at from Phase 1A, and continue to the west towards Cleveland Ave.

Utility Work Starting—Monday, June 14

Glenpaul Ave was reclaimed earlier in the week and tree removals wrapped up throughout the neighborhood. Temporary water is setup on the east block of Glenpaul (Phase 1B) with hookups to individual houses occurring on Monday, June 14. C&L will be stripping off the reclaim material along all of Glenpual Ave on Monday, June 14, which will cause minor traffic interruptions.

C&L Excavating is scheduled to start watermain work along Glenpaul Avenue, east of Prior Ave (Phases 1A) on Monday, June 14Watermain installation will begin with a cut and cap on Monday at Prior & Glenpaul, and a connection at New Brighton and Glenpaul. Watermain work would then continue from New Brighton and work towards Prior.

Temporary water setup on the west block of Glenpaul (Phase 1Bhas begun, with hookups to individual homes occurring next week. Watermain work will start on Phase 1B later in the week, tentatively Thursday, June 17 or Friday, June 18, directly following the watermain work on Phase 1A. The work will likely start at Prior Ave and move toward Cleveland Ave.

Individual water services on Glenpaul will be installed following the completion of the watermain, tentatively during the week of June 21.

Phases 2 and 3 have flipped schedules! Jerrold Ave (the reconstruction area with no existing curb) will now be Phase 2 and will start in Mid-July when the utility work is wrapping up on Glenpaul Ave. Prior Ave will now be Phase 3 and will start in August when the utility work is wrapping up on Jerrold Ave.

Construction Starting—Monday, June 7

C&L Excavating is scheduled to reclaim (grind up) the existing asphalt street pavement along Glenpaul Avenue (Phases 1A & 1B) on Monday, June 7. Temporary water setup on the east block of Glenpaul (Phase 1A) will also begin on Monday, June 7, with hookups to individual homes occurring later in the week. Tree removals are scheduled to begin on Wednesday, June 9 and will occur throughout the neighborhood (all phases). Trees to be removed as part of the project will be marked with a ribbon earlier in the week. 

Driveway removals and utility work on the east block of Glenpaul (Phase 1A) is scheduled to begin on Monday, June 14.

A newsletter is in the mail with additional details, but please reach out to Brian Schmit (612-368-1228) or Nick Amatuccio (612-965-3926) with Bolton & Menk or David Swearingen (651-792-7847) with the City of Arden Hills if you have any questions about the project.

Construction StartingWeek of June 7

C&L Excavating will start construction in the neighborhood during the week of June 7. During this week, residents should expect to see traffic control setup, tree removals throughout the neighborhood, and temporary water setup on the east block of Glenpaul Avenue (Phase 1A). Pavement removals on Glenpaul (Phases 1A & 1B) will begin during the week of June 14, with utility work on the east block of Glenpaul (Phase 1A) immediately following pavement removals.

Gas main work on Jerrold Ave—Week of April 26

Gas main and service replacement by Xcel Energy on Jerrold Avenue is scheduled to be completed the week of April 26. Turf restoration in disturbed areas will follow shortly after. If you have any questions or concerns regarding the gas main work by Xcel, you can contact the Scott Widmer at 651-261-3087. 

Contact Us

As always, feel free to reach out to Nick Amatuccio (952-890-0509 ext. 2900) with Bolton & Menk or David Swearingen (651-792-7847) with the City of Arden Hills if you have any other questions about the project.

Hazelnut Park/Glenpaul Area Street Improvements 2021

Project Overview

The city has started data collection and project planning for proposed street and utility improvements within the Hazelnut Park Neighborhood anticipated for the 2021 construction season. Planning work also includes an evaluation of pavement and utilities along Lake Valentine Road.

Project Scope

The project study includes the following street segments.

  • Glenpaul Avenue from New Brighton Road to Cleveland Avenue
  • Edgewater Avenue from New Brighton Road to the west end of the cul de sac
  • Jerrold Avenue from New Brighton Road to the west end of the cul de sac
  • Prior Avenue from County Road D to Jerrold Avenue

Project Timeline

The project team is currently designing the project based on the results of the project feasibility study.  A copy of the feasibility study is available below. The project is scheduled for public bidding in January 2021, with construction starting in April/May 2021.

Project Presentations

Public Informational Presentation for 2021 PMP
(posted April 14, 2021)

Presentation (posted October 22, 2020) describing the design, schedule, cost, and assessments for the project.

First Project Planning Informational Presentation - Recorded May 2020 describing the study and potential street and utility improvements.

Project Mailings

Project Notice Letter and Map (May 2020) (PDF)

Notice of Field Survey (August 2020) (PDF)

Project Improvement Notice of Public Hearing (August 2020) (PDF)

Public Informational Meeting Invitation (October 2020) (PDF)

Project Feasibility Report

The City Council accepted the project Feasibility Report on July 27, 2020.  The report outlines the recommended project components, costs and funding sources.  A copy of the report is available here.

Assessment Roll

To access a copy of the special assessment roll contained in the Feasibility Report, click here

Location and Proposed Plan

2021 PMP MAP (PDF)

Contacts

David Swearingen, Interim Public Works Director
City of Arden Hills
651-792-7847
Email David Swearingen 

Nick Amatuccio, Bolton & Menk
612-965-3926

Brian Schmit, Bolton & Menk
612-368-1228

2021 PMP Proposed Plan for Hazelnut Park Neighborhood

PROJECT CONTACTS

David Swearingen  Interim Public Works Dir. 651-792-7847
Nick Amatuccio Bolton & Menk 612-965-3926
Brian Schmit Bolton & Menk 612-368-1228